Assam
Doyang Reserve Forest region including adjacent areas like Negheribil Merapani, Bhelouguri, Uriamghat, and adjoining villages; Bordering Nagaland (Merapani area); Nambor/South Nambar Reserve Forests
,
Doyang
,
Golaghat
Published :
Mar 2026
|
Updated :
Forest conservation and community land rights: The Doyang Reserve Forest eviction case in Golaghat, Assam
Reported by
East Street Journal Asia
Legal Review by
Anmol Gupta
Rakshit Dhingra, Amrita Chekkutty
Edited by
Anupa Kujur
146
Households affected
205
People affected
1968
Year started
40.14
ha.
Land area affected
146
Households affected
205
People Affected
1968
Year started
40.14
Land area affected
Key Insights
Sector
Conservation and Forestry
Reason/Cause of conflict
Forest Administration (Other than Protected Areas)
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Unclassifed
Sector
Conservation and Forestry
Reason/Cause of conflict
Forest Administration (Other than Protected Areas)
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

On 8 August 2025, the Assam Forest Department demolished 146 illegal houses and evicted 205 people from the Doyang Reserve Forest in Golaghat district to reclaim over 300 bighas (40 hectares) of reserved forest land.

A district administration official told the Times of India that notices were served to the families on 24 July 2025, asking them to vacate the land within seven days. Following which, two writ petitions were filed by a few people of Negheri Bil claiming land rights and praying to treat the notices as 'ignored'. A single-judge bench of the court on 29 July extended the eviction window until 7 August 2025 and instructed the state government to initiate steps for eviction and conservation of the forest land after the deadline.

The petitioners again approached the two-member division bench of Chief Justice Ashutosh Kumar and Justice Arun Dev Choudhury by filing a writ appeal, in which the court on 5 August granted the petitioners a 10-day window, until 14 August, to either submit proof of land allocation or vacate. Till then, the government was directed not to take any coercive steps against the appellants. Adhering to the orders, the Forest Department and the district administration left houses of 59 appellants untouched and demolished the others.

In court, authorities framed the action as forest conservation and enforcement of law, while local administration and Forest Department affidavits to the Gauhati High Court stated that large tracts of encroachment have been cleared historically.

On 18 August 2026, the Gauhati High Court directed families residing inside the Doyang and Nambor reserve forests in Golaghat district to vacate the land within seven days, ruling that no encroacher can claim legal rights over reserved forest land. The ruling dealt a blow to hopes of 74 petitioners who challenged eviction notices, citing the Assam Land and Revenue Regulation of 1886, the Assam Land Policy of 2019, and a Supreme Court directive from December 2024. The bench, however, dismissed the arguments, noting that the petitioners had failed to provide valid documents to establish their land rights despite being given ten days earlier this month to do so.

In October 2025, residents of Doyang resolved to escalate their century-old struggle for land rights amid growing frustration over unmet demands. Residents have been demanding legal land ownership stating that the community has been in continuous settlement in Doyang for over 120 years. They allege that successive governments have repeatedly failed to deliver on promises to grant pattas (land ownership deeds), leaving residents with no option but to intensify their agitation.

While communities argued that evictions violate ancestral rights, the Assam government defended its move, adding that such action against encroachers would continue.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for legal recognition of land rights

Demand for promised land

Other Demand/Contention of the Affected Community

Demand to halt to evictions;

Region Classification

Rural

Type of Land

Common

Forest

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land, Residential area, Other Natural Resource extraction/dependence, Water bodies

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Assam Forest Department; District Administration (Golaghat); Ministry of Environment, Forests and Climate Change;

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

NEEPCO (operator of Doyang hydro facility)

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Local residents

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Show more work
Fact sheet

Demand/Contention of the Affected Community

Demand for legal recognition of land rights

Demand for promised land

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land, Residential area, Other Natural Resource extraction/dependence, Water bodies

Whether the project was stalled due to land conflict

Source/Reference