Himachal Pradesh
,
Sawra-Kuddu
,
Shimla
Published :
Sep 2016
|
Updated :
Courts Order Higher Compensation for Families Affected by Sawra-Kuddu Hydro-Electric Project in Shimla
Reported by
Lokendra
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
587
Households affected
2818
People affected
2007
Year started
98
Land area affected
587
Households affected
2818
People Affected
2007
Year started
98
Land area affected
Key Insights
Sector
Power
Reason/Cause of conflict
Hydroelectric Project
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Power
Reason/Cause of conflict
Hydroelectric Project
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

In 2015, the locals in Thana Plaun and Mandal villages, a landslide-prone zone, opposed the ongoing construction of an additional edit tunnel for the Sawra – Kuddu Hydro Electric Project (HEP).
The 111 Megawatt HEP is a run-of-the-river project on the Pabbar river, a tributary of Yamuna, in the Shimla district of Himachal Pradesh. The work for the project started in 2007, and the Himachal Pradesh Power Corporation Limited (HPPCL) undertook the execution. It is a part of the Himachal Pradesh Clean Energy Development Program funded by the Asian Development Bank. The project’s investment cost increased from the initial estimation of INR 558.53 crore to INR 1,165.10 by 2017, according to a 2014 CAG report, which also highlighted the possibility of the project turning commercially unviable.  
In May 2015, the affected farmers, whose villages were underneath the tunnel, started to agitate and demanded an immediate ban on constructing the 424-metre long tunnel. As per a news report, the local leaders allege that the corporation did not acquire a No Objection Certificate from the gram panchayat before starting the construction. A protesting leader from State Kisan Sabha claimed that the additional tunnel was being constructed rashly to “achieve the deadline” after multiple delays. There were also claims that the tunnel did not get an environmental clearance. However, the corporation refuted these claims. It stated that the tunnel would not affect the villages and had received the due clearances, according to another news report
Following the protests, a representative from Thana Gram Panchayat filed an affidavit with the National Green Tribunal. They [claimed](http://cimfr.csircentral.net/2360/1/Evaluating the sustainability of a hydropower project in theHimalayas A case study for resolving legal disputes in tribunals.pdf) that the houses in the village suffered cracks due to the vibrations from the blasting activities, and it adversely affected their apple orchids. The affected families also raised concerns over the drying up of water sources in the region, and the fear of soil erosion. 
In July 2015, NGT [halted](https://www.hindustantimes.com/punjab/ngt-orders-halt-to-tunnelling-work-at-hydel-project/story-g146uDuuKjPeI1Qz7dvKdL.html /) the construction to investigate these claims. 
Subsequently, on March 23, 2016, the NGT ordered HPPCL to compensate the households which suffered damage in 90 days, stated a news report. It also directed the state government to adopt necessary measures to protect the region, and avoid causing any further damages. One such directive was to formulate a committee to survey the affected area and recommend a “revival plan” for the water sources, which were drying up. However, NGT did not rule to stop the construction. Instead, it cautioned the villagers against causing any obstructions to the process. 
Earlier, some of the project affected villages had also appealed in the Shimla High Court against the low compensation offered for the land acquisition from the eight panchayats. On October 12, 2018, the court revised the compensation rates and directed the corporation to distribute benefits to all the affected families, even if they did not approach the court. 
As per the news reports, the project was finally commissioned in April 2020, after a delay of over seven years. However, many of the affected families are yet to receive compensation. A news report published in February 2021 noted that the directives given by the NGT were not followed through by the administration, and the households in Thana village continued to struggle for water supply. 
In Thana village, only about 40% of the affected households had received compensation even after the HEP has started, Manshi Asher, a representative from the Himdhara collective, informed Land Conflict Watch. Based on her discussions with a local, she stated that the rest were yet to receive a final decision on the compensation, and the issue of dried water sources is still not resolved. 

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for compensation

Opposition against environmental degradation

Demand for promised compensation

Complaint against procedural violations

Demand to retain/protect access to common land/resources

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Common and Private

Forest and Non-Forest

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Project completed

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Other Natural Resource extraction/dependence, Agricultural land

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

1165

Type of investment:

Revised Investment

Year of Estimation

2007

Page Number In Investment Document:

10

Has the Conflict Ended?

Yes

When did it end?

October 2018

Why did the conflict end?

Court decision in favour of community

In relation to the claim of NoC and environmental clearnace, , NGT NGT did not rule to stop the construction. Instead, it cautioned the villagers against causing any obstructions to the process. In addition it also ordered, HPPCL to compensate the households which suffered damage in 90 days. Shimla HIgh Court revised the compensation rates and directed the corporate to distribute benefits to all the affected families, even if they did not approach the court.

4
Additional Information

Government Departments Involved in the Conflict:

District Administration, Shimla

PSUs Involved in the Conflict:

Himachal Pradesh Power Corporation Limited

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Patel Engineering

Did LCW Approach Corporate Parties for Comments?

No

Communities/Local Organisations in the Conflict:

Himachal Kisan Sabha

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Lokendra
Show more work
Latest updates
East Jaintia Hills
Meghalaya

Violent protest during public hearing for cement plant expansion in Meghalaya's East Jaintia Hills

Narela
Delhi

Residents of Narela's Bajitpur Thakran oppose demolition of temples for defence institute, demand sports complex

Surguja
Chhattisgarh

Adivasis in Chhattisgarh's Hasdeo protest relentlessly against mining project in forest

Kamrup Metropolitan
Assam

Lawyer bodies protest against Assam government’s decision to relocate Gauhati High Court

Faizabad
Uttar Pradesh

Demands for Ram Temple, Babri Mosque at same site divides Ayodhya

Mumbai
Maharashtra

Supreme Court Allows Land Reclamation for Mumbai Coastal Road Project

Pune
Maharashtra

Farmers Refuse Land for Pune Outer Ring Road Project in Maharashtra

Surat
Gujarat

Slum Dwellers in Gujarat's Surat Stage Protest against Demolition, Forced Eviction

Fact sheet

Demand/Contention of the Affected Community

Demand for compensation

Opposition against environmental degradation

Demand for promised compensation

Complaint against procedural violations

Demand to retain/protect access to common land/resources

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Project completed

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Other Natural Resource extraction/dependence, Agricultural land

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us