Tezpur University raises concerns over PWD's road-widening project
Reported by
Emilo Yanthan
Legal Review by
Anmol Gupta
Sourabh Rai, Amrita Chekkutty
Edited by
Anupa Kujur
Households affected
People affected
2024
Year started
ha.
Land area affected
Households affected
People Affected
2024
Year started
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
1
Summary

In December 2024, a conflict broke out between the Tezpur University staff and PWD officials over an expansion of a road that links Poruwa Chariali with National Highway 15.

Tezpur University Teachers' Association (TUTA) alleged that the road expansion would result in the destruction of the historic Main Gate of TU, designed based on the sketch of Jyoti Prasad Agarwala, being closed down permanently. In addition, they alleged that the expansion work could cause structural risk to the boundary wall of the campus, an animal house and a laboratory equipment, which are close to the boundary region.

A delegation from the university issued a memorandum to Sonitpur district commissioner Ankur Bharali on 11 December 2024, expressing dissatisfaction over the matter. The memorandum stated, “There is a lot of anguish among the University community regarding the unscientific widening of the road. This may boil over into agitation if timely action is not taken in the right spirit.”
 
Prof Shambhu Nath Singh, the vice chancellor of TU clarified that the road's expansion will be a threat to the university and impede its infrastructure and safety. He added that the university has already expressed their concerns to Assam CM in a letter dated 27.09.2024.

The university also submitted a letter to the additional chief engineer of PWD (Roads), Tezpur Zone, on 27 November 2024, raising safety concerns as the widening of the road would lead to the reduction of the gap between the gate and the new road.  

2
Fact Sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

Other Demand/Contention of the Affected Community

Region Classification

Urban

Type of Land

Common

Non-Forest (Other than Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Sonitpur District Administration, Tezpur University, PWD (Roads) Tezpur zone

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Tezpur University Teachers' Association (TUTA)

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Show more work
Fact sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us