Chhattisgarh
,
Nakti
,
Raipur
Published :
Aug 2026
|
Updated :
Housing development and forced eviction: The Nakti village demolition conflict in Chhattisgarh
Reported by
Hritik Bhatnagar
Legal Review by
Anmol Gupta
Rakshit Dhingra, Amrita Chekkutty
Edited by
Anupa Kujur
85
Households affected
408
People affected
2026
Year started
29.17
ha.
Land area affected
85
Households affected
408
People Affected
2026
Year started
29.17
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Other Kind of Infrastructure
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Unclassifed
Sector
Infrastructure
Reason/Cause of conflict
Other Kind of Infrastructure
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

In 2020, the Congress government proposed that a portion of a 15.5-hectare parcel in Nakti village, near Raipur, be used by the Chhattisgarh Housing Board for a general residential colony. The land is recorded as government grazing land under Khasra No. 460 and falls within the jurisdiction of the New Raipur Development Authority (NRDA).

In June 2026, the Chhattisgarh government demolished 85 houses on the same parcel, alleging that they had been constructed on government land. Villagers clashed with the police and government officials, even throwing stones at them, during the anti-encroachment drive. They said that the demolished houses included those that had been allotted under government schemes such as PM Aawas and Indira Aawas Yojana and the drive had been carried out without “properly rehabilitating” the affected families.

The district administration, however, told The Hindu that it was making arrangements to accommodate all the encroachers in the houses located in Sector-30 of Naya Raipur. 

In a letter dated 25.9.2024, the Secretary of the Housing and Environment Department had directed the removal of any encroachment and allocated land for six Khasra numbers in Nakti. The order directed the Raipur Collector to allocate approximately 29.18 hectares of the land for a housing colony for MLAs and MPs of the current Chhattisgarh Assembly and clear the area. 

Residents also alleged that Raipur MP Brijmojan Agrawal had met with them just two days before the demolition and assured them of no action, especially during monsoon. The administration maintained the demolition followed due process and that 77 individuals whose homes were demolished were encroaching on the government’s land. 

At least 66 displaced families were allotted Economically Weaker Section (EWS) flats in Sector 30, Nava Raipur, and the rest were offered temporary accommodation. According to authorities, the other residents' cases only involved boundary walls and were not directly affected by the demolition. They also own houses in the village, which makes them ineligible for rehabilitation under the current norms. 

Families questioned the basic safety and quality of the allotted housing, citing the lack of water and electricity connections and broken or unusable bathrooms, particularly located on the top floors of the building. Local people also questioned how the same people were offered PM Awas Yojana and basic amenities like electricity and water connections if they were encroachers. Some of the locals also alleged that a complaint filed by a person from Bhilai in Durg district served as a trigger for the demolition.

On 2 July, villagers staged an 11-hour sit-in at the Raipur Collectorate. The protest was called off following talks with the administration, but protesters issued a 24-hour ultimatum, warning of an indefinite sit-in and a jail bharo movement if their demands were not addressed. 

On 4 July, displaced residents, accompanied by Congress leaders, protested outside the Chief Minister Vishnu Deo Sai’s residence, demanding compensation and restoration of their land. They also demanded withdrawal of FIRs against villagers, who earlier warned of intensifying demonstrations if the demands were not met. 

2
Fact Sheet

Demand/Contention of the Affected Community

Complaint against procedural violations

Demand for rehabilitation

Demand for legal recognition of land rights

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Common

Non-Forest (Other than Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Bharatiya Nyaya Sanhita, 2023

Section115(2) [Voluntarily causing hurt], Section 121[Voluntarily causing hurt or grievous hurt to deter public servant from his duty.]; Section 191(1), 191(2) [Rioting]

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Grazing, Dwelling/habitation use

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Raipur District Administration, Housing Board, Collector, Finance Minister

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Bharatiya Nyaya Sanhita, 2023

Section115(2) [Voluntarily causing hurt], Section 121[Voluntarily causing hurt or grievous hurt to deter public servant from his duty.]; Section 191(1), 191(2) [Rioting]

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us