Gujarat
,
Yavarpura
,
Banaskantha
Published :
Jan 2026
|
Updated :
Electricity poles on farmland: Right-of-way disputes in the farmers–GETCO conflict at Gujarat's Yavarpura village
Reported by
Suchak Patel
Legal Review by
Anmol Gupta
Rakshit Dhingra
Edited by
Anupa Kujur
387
Households affected
2367
People affected
2025
Year started
ha.
Land area affected
387
Households affected
2367
People Affected
2025
Year started
Land area affected
Key Insights
Sector
Power
Reason/Cause of conflict
Transmission Lines
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Unclassifed
Sector
Power
Reason/Cause of conflict
Transmission Lines
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

A tense confrontation erupted between farmers and officials of the Gujarat Energy Transmission Corporation (GETCO) in Yavarpura village of Deesa taluka in Gujarat's Banaskantha district. The dispute arose over the installation of electricity poles on their land without prior notice or consent.

In October 2025, the GETCO team, accompanied by police personnel, began surveying the fields and digging pits for electricity poles. The farmers, who claim they were not informed about the project, objected strongly to the work. "We were not consulted, and now our grazing land is being disrupted. If the poles are installed here, we should be paid rent or given alternative land," a farmer told Bhaskar.

Despite repeated appeals from the farmers to halt the work and allow them two days to present their case to the government, officials reportedly continued with the survey and construction activities. The presence of police further escalated tensions, leading to a heated exchange between farmers and GETCO staff. Several farmers accused the company of attempting to intimidate them to facilitate the project.

Local residents expressed concerns over the loss of farmland and grazing areas, stressing that smaller landholders are disproportionately affected. "The police are scaring us, but we will fight for our land. This is a conspiracy to benefit companies at the expense of farmers," said another farmer.

Banaskantha has witnessed several such disputes over land acquisition in recent years. Farmers had previously protested the Bharatmala project, citing inadequate compensation. The current conflict over the GETCO electricity line has once again highlighted the growing tensions between farmers and authorities over land rights and livelihoods.

As of now, farmers have threatened a large-scale agitation and expressed plans to approach the High Court if their demands are not addressed. While the project aims to strengthen the state’s electricity infrastructure, it comes at a significant cost to farmers, raising concerns over equitable compensation and land acquisition practices.

LCW researcher filed an RTI with the Banaskantha district administration seeking details of citizen complaints and the action taken on them. The authority did not share the information. However, in its reply, the Public Information Officer stated that no letters had been exchanged between the district administration and GETCO.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for compensation

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Private

N/A

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

PSUs Involved in the Conflict:

Gujarat Energy Transmission Corporation Limited (GETCO)

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Suchak Patel
Suchak is an independent researcher.
Show more work
Fact sheet

Demand/Contention of the Affected Community

Demand for compensation

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land

Whether the project was stalled due to land conflict

Source/Reference