Delayed and disputed: Unfair compensation fuels farmers' resistance at Buxar Thermal Power Plant
Reported by
Rahul Kumar Gaurav
Legal Review by
Anmol Gupta
Sourabh Rai, Amrita Chekkutty
Edited by
Anupa Kujur
1000
Households affected
4800
People affected
2022
Year started
506
ha.
Land area affected
1000
Households affected
4800
People Affected
2022
Year started
506
Land area affected
Key Insights
Sector
Power
Reason/Cause of conflict
Thermal Power Plant
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Unclassifed
Sector
Power
Reason/Cause of conflict
Thermal Power Plant
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

In March 2024, a clash broke out between farmers and police in Bihar’s Buxar district over land acquisition and compensation disputes related to the under-construction Chausa Thermal Power Plant, a joint venture between the Government of India and the Himachal Pradesh Government. On 20 March 2024, farmers blocked the plant's main gate, prompting the police to lathi charge, injuring at least 20 personnel.

Earlier in January 2024, the Patna High Court had ordered the district administration to monitor the site and prevent gathering of protestors in active work zones. Since October 2022, farmers have staged several protests demanding fair compensation for the land acquired by Satluj Jal Vidyut Nigam (SJVN) between 2012 and 2013 for the thermal plant in Chausa village.

This project was proposed in 2012-13 and in 2015, the responsibility of its construction was given to Satluj Jal Vidyut Nigam (SJVN). For the project, 1058 acres of land was to be acquired for the main plant, 147 acres for the rail corridor to be built to bring coal to the plant and 45 acres of land for the pipeline to bring water from Ganga. The Prime Minister laid the foundation stone of the plant in March 2019. By January 2023, the district administration acquired over 1,000 acres of land for the project from local farmers, while efforts were underway to acquire the remaining 250 acres of land for a rail corridor and a water pipeline.

According to a Bhaskar report, most of the 300 farmers, who received 80 percent of their total compensation in 2012-13, alleged that they have been given less compensation. In addition, farmers who received the payment between 2014 and 2016 claimed that the compensation was affixed at the circle rate from 2011. Meanwhile, Buxar-based RTI activist Shiv Prakash Rai alleged that the authorities began acquiring 250 acres of land without the approval of farmers. Farmers also alleged that at the time of acquisition they did not know why the land was being acquired and what compensation would be given for it.

Despite repeated protests since August 2022, SJVN and government agencies have continued construction. In January 2023, work on the water pipeline was forcibly started on the land of Jai Mangal Pandey and Bharat Pandey in Chausa Nagar Panchayat. In protest, farmers shut down the main gate of the under-construction power plant. This led to clashes between police and farmers. In Banarpur village, police reportedly used force against women, minors, and young girls, a video of which went viral. In retaliation, angry villagers set fire to dozens of vehicles inside the plant premises, turning the farmer protest into a political flashpoint. More than 39 individuals were named in FIRs, with over 300 others unnamed, in connection to the violence.

According to the farmers, 90 percent of the farmers have not taken compensation and those who have taken it, have taken it by expressing objection.

In October 2023, the district administration formed a mediation committee, led by SDM Dhirendra Mishra, to facilitate talks. Mishra criticized SJVN officials, asserting that farmers' rights would not be compromised. The matter is currently under judicial review in the LAR (Land Acquisition, Rehabilitation) Court, and farmers have stated they are willing to abide by the court’s decision.

2
Fact Sheet

Demand/Contention of the Affected Community

Complaint against procedural violations

Demand for more compensation than promised

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Private

What was the action taken by the police?

Arrest

How many people did the police detain or arrest?

30

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Project stalled due to protests

Original Project Deadline

2023

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Agricultural land

Whether the project was stalled due to land conflict

Yes

Source/Reference

Around three and a half thousand workers working at the Chausa Thermal Power Plant of Buxar district went on strike in 2023 demanding better salaries.

Total investment involved (in Crores):

11000

Type of investment:

Cost of Project

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

No

Communities/Local Organisations in the Conflict:

5
Information on the use of criminal law

What was the action taken by the police?

Arrest

How many people did the police detain or arrest?

30

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Show more work
Fact sheet

Demand/Contention of the Affected Community

Complaint against procedural violations

Demand for more compensation than promised

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Project stalled due to protests

Original Project Deadline

2023

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Agricultural land

Whether the project was stalled due to land conflict

Yes

Source/Reference

Around three and a half thousand workers working at the Chausa Thermal Power Plant of Buxar district went on strike in 2023 demanding better salaries.